Wednesday, March 23, 2011

Second Foundation

So far I've only posted pictures of things being torn down or dug out... finally I can start posting some pictures of the house being built back up!


The foundation for the new back part of the house was built over most of a week, from 2/22/11 to 2/27/11.
South wall of the foundation frame is in place to hold the cement while it sets

Foundation frame west wall.  The opening there will be for the doorway leading out to the backyard

Foundation frame north wall

The new foundation is fully set, frame is gone

This will eventually be the stairway from the backyard down to the basement.  Since this part of the foundation will be very visible, Larry put in some paneling texture to the walls which you can see here on the inside of the stairwell.

That's the temporary door to the basement where I took a lot of the other pictures from

Walkway on the north side of the house... this was eventually dug out to allow for repair and waterproofing to the existing foundation

Another view of the future stairway to the basement

South wall of the foundation and part of the stairs/doorway to basement

No comments:

Post a Comment